After weeks of preparation and planning, professionals from departments across CAP entered the penstock at Waddell Pump Generating Plant to conduct a five-year inspection. The penstock is a 14-foot diameter, pressurized pipe that is used to transport water into and out of the lake, spinning turbines that generate electricity.
Jeff Denning, supervisor of Waddell Pump Generating Plant, said the one-quarter mile long pipe is a critical piece of infrastructure, and this inspection is an important way of ensuring its reliability.
Before the inspection, they shut down four of the plant’s eight pumps, set stop logs, and drain all the water, which takes approximately one week. Then the group – including engineers, mechanics, coaters, planners and safety professionals – grab their flashlights and head into the pipe, which sits 144 feet below the surface.
“It’s a slow process as we make our way through the pipe, inspecting the condition of everything, such as coatings, concrete, gates, flow meters,” said Denning. “If we find anything, we have an expert right there to examine it.”
Denning said they were happy to report that they didn’t find anything concerning.
“This inspection was a true collaborative effort between many groups and we are extremely appreciative of all the work,” said Denning.